PAWS 16 station 5C collet system on a hydraulic base plate

The Hidden Opportunity in Workholding: Parts Per Shift

If the number of parts per shift in your production milling operation decides your profitability, your fixture is part of the answer. Many manufacturers focus on hitting a quoted cycle time, so workholding ROI (return on investment) gets judged on the cut alone. This guide looks at the other half of run time, the seconds spent loading, unloading, changing tools and seating parts, and at what a fixture can do about them. It is built on our own analysis, Hidden Opportunity in Workholding, and on the formulas inside our free ROI calculator.

Key takeaways

  • Feed time, the time the CNC (computer numerical control) machine is actually cutting, is on average only 40 to 50 percent of overall run time.
  • In an illustrative example worked with our calculator’s formulas, holding 12 parts per cycle instead of 2 raises output from 570 to 719 parts per 8-hour shift, about 26 percent.
  • In the turntable model in our analysis, holding 16 parts with automated clamping instead of 1 part in a hand-clamped vise takes parts per shift from 577 to 922.
  • A custom fixture that does this has a typical lead time of 8 to 10 weeks.

Where Does Run Time Go? Machine Utilization Beyond Feed Time

Feed time is on average only 40 to 50 percent of run time; the rest is non-cutting time.

Manufacturing managers typically seek productivity gains through their knowledge of tooling, feeds and speeds. Reducing cycle times through feed time improvements is a worthy endeavor. But if you study the run time of the average job in your milling department, you will find that feed time is on average only 40 to 50 percent of overall run time. That figure is from our Hidden Opportunity in Workholding analysis. Your shop’s number is the first thing worth measuring.

Run time is the period from the moment the operator hits cycle start until the next time the operator hits cycle start. It includes the cut, the tool changes, the rapids, the probing and, on a machine without a pallet changer or turntable, the load and unload.

That is why machine utilization is not the same thing as cycle time, and why spindle utilization is the number to watch. A machine can run all shift with the spindle cutting for half the time or less. Raising spindle uptime means going after the non-cutting half, and your workholding choices decide much of that half.

What Are the Six Non-Cutting Costs?

Load and unload, tool changes, probing, rapid moves, part seating and operator attendance.

Our analysis asks a set of questions about non-feed time. Each answer is a cost you pay every cycle.

1. Load and unload: your CNC load time

Does your team count the operator attendance needed to load and unload the machine? In the single-part vise example from our analysis, clamping and unclamping, loading and unloading take 16 seconds per cycle. Blowing off parts and fixture takes 5 more, setting parts with a hammer 5, opening and closing doors 5 and pressing cycle start 3: 34 seconds of operator tasks per cycle. On a machine without a pallet changer, every one of those seconds is added to run time.

2. Tool changes: non-cutting time between tools

Every tool change costs chip-to-chip time, which is the tool change plus the motion to and from the workpiece. The turntable mill in our analysis does it in 1.7 seconds; our calculator notes that most vertical machining centers (VMCs) are in the 6 to 9 second range. With 10 tools per cycle, that is 17 seconds of non-cutting time per cycle at 1.7 seconds, and 60 to 90 seconds at 6 to 9.

3. Probing and tool verification

In turntable environments, most of the non-cutting time is tool changes, probing, tool verification and rapid movements. Probing protects quality, and on many jobs it runs every cycle.

4. Rapid moves

Does your team count the cost of all the rapids? Rapid traverse between features and parts adds time that no feed rate improvement will touch. In our analysis, feed and rapid time together come to 30 seconds per part.

5. Seating parts: where to reduce load time on a machining center

Is anyone aware of the time the operator spends seating parts or blowing off fixturing and parts? In the 16-part example from our analysis, setting parts with a hammer takes 32 seconds per cycle. Our Dead Blow Eliminator makes part seating part of the CNC program, with a consistent and adjustable impact force, which leads to less operator fatigue and shorter load times.

6. Operator attendance

Is the operator tied to one machine because of all these tasks? Or worse, are your parts per shift operator dependent? In the single-part example, the operator is needed at the machine 577 times a shift. Labor is often overlooked in a turntable environment, where most consider operator time free because the machine keeps running during loading. With roughly twice as much available time, operators could run multiple machines, perform more quality checks or produce more parts each shift with less fatigue.

How Much Does Part Density Add? 2 Parts vs 12 Parts Per Cycle

In the worked example, about 26 percent more parts per shift: 570 to 719.

More parts under the spindle means fewer tool changes per part and fewer load sequences per shift. As our ROI calculator puts it, it is a wonderful thing to understand the efficiency differences between holding two parts or twelve when you are trying to hit production deadlines and profitability goals. Here is that comparison, worked with the calculator’s own formulas on inputs drawn from our analysis and the calculator.

Inputs (illustrative):

  • 10 tools per cycle at 1.7 seconds chip-to-chip, and 30 seconds of feed and rapid per part (from our analysis). A 2-part cycle is therefore 77 seconds, 17 of them tool changes.
  • A 2-part load time of 24 seconds: the 16-second single-part clamp and load time from our analysis plus the calculator’s estimate of 8 seconds for each extra part.
  • A 12-part load time of 104 seconds, the calculator’s own estimate (24 seconds plus 10 extra parts at 8 seconds).
  • An annual quantity of 100,000 parts and the calculator’s $75 an hour for machine time.
Measure 2 parts per cycle 12 parts per cycle
Cycle time, without load (seconds) 77 377
Load time (seconds) 24 104
Run time, cycle start to cycle start (seconds) 101 481
Share of the cycle spent on tool changes 22.1% 4.5%
Parts per 8-hour shift 570 719
Tool changes per shift 2,851 599
Tool change time per shift (minutes) 80.8 17.0
Load sequences per shift 285 60
Time between loads (minutes) 1.3 6.3
Machine hours for 100,000 parts 1,402.8 1,113.4
Machine hours saved, valued at $75/hour 289.4 hours, $21,701
Parts per 8-hour shift 0 160 320 480 640 800 960 5702 parts (worked example) 71912 parts (worked example) 5771 part (turntable model) 92216 parts (turntable model) Worked example: ROI calculator formulas, illustrative inputs. Turntable model: Hidden Opportunity in Workholding.

Parts per shift rise about 26 percent, from 570 to 719, and tool change time per shift falls from about 81 minutes to 17. The operator loads the machine 60 times a shift instead of 285 and gets about five more minutes between loads to run a second machine or check parts. Load time grows more than fourfold and the gain still holds, because the load is spread over 12 parts. These figures assume 100 percent efficiency, as the calculator does; your load time, tool count and cycle will differ. We used only the clamp-and-load time; adding blow-off, seating and door time makes the gain larger.

Our turntable model goes further, because loading happens while the machine cuts. Holding 16 parts in an automated clamping system instead of hand clamping 1 part on a vise:

  • Parts per shift go from 577 to 922, a 60 percent increase.
  • Tool changes go from 5,772 to 571 per shift, and tool change time from 162 minutes to 16.
  • The operator is needed at the machine 58 times instead of 577.
  • Task hours per shift fall from 5.4 to 2.5, and operator tasks from 2,885 to 290.

What Does Automation Add? Hydraulic Clamping and Part Seating

With a multiple-part system that incorporates automated clamping, productivity increases of 35 percent or more are possible.

Density sets how many parts share each tool change. Automation sets how fast those parts load. By utilizing a multiple-part workholding system that incorporates automated clamping, it is possible to achieve productivity increases of 35 percent or more, and operator attendance can be reduced by as much as 50 percent.

  • Hydraulic clamping. M-Code (machine code) fixture clamp and unclamp, the same clamping force on every load, and system pressure detection safeguards.
  • Pump packages. Our single-pallet and dual-pallet pump packages clamp or unclamp with a flip of a manual control valve lever, the simpler, lower-cost option, mounted on the pump or on the PAWS Workholding system, or with M-code activation through 24 volt solenoids on the pump, commanded by the machining center’s control. The standard porting block with quick disconnects is interchangeable with the control lever block or an accumulator package, and pressure sensing is optional.
  • Part seating. The Dead Blow Eliminator replaces the dead-blow hammer with a programmed, adjustable impact.
  • Quality and fatigue. Consistent clamping force and pressure hold every part, and operators no longer face the torque of a drill or vise handle on their joints.

Run Your Own Numbers: The Workholding ROI Calculator

This calculator uses the same formulas as our downloadable Multiple Part Workholding ROI Calculator, plus a field for your own machine-time rate. Enter your current process, then the number of parts you want under the spindle. The new load time fills in with the calculator’s estimate of 8 seconds per extra part; type over it if you know better. The old adage is true: good data in will get you pretty good data out.

ResultTodayNew fixture

Prefer the spreadsheet? Download the ROI calculator (Excel).

Take It Into the Meeting: The Two-Page Worksheet

The parts-per-shift worksheet (PDF) puts the calculator’s fields on one printable page and adds a second page with the figures in this guide: the worked example and the turntable model. Fill it in at the machine, then bring it to the meeting where the fixture gets approved.

Download the worksheet (PDF)

How Long Does a Fixture Like This Take?

Lead time for custom fixtures is typically 8 to 10 weeks.

Every custom fixture is quoted for your part, your process and your production volume.

In the worked example, the 12-part fixture saves about 289 machine hours per 100,000 parts, about $21,701 at the calculator’s $75 an hour. Your volume, part count and current process decide how fast a fixture pays for itself, which is why we start every project with the numbers. See how we design and build custom workholding fixtures, or talk with an application engineer.

Frequently Asked Questions

What is workholding ROI?

It is the return on a fixture measured in output: more parts per shift, fewer tool changes and load sequences per part, and fewer machine hours per job. The downloadable spreadsheet values machine time at $75 an hour, a rate you can change in the sheet; the calculator on this page has a rate field.

How do I measure spindle utilization on a production mill?

Time a full run, from cycle start to the next cycle start, then add up the time the machining center is actually cutting. The rest is non-cutting time: tool changes, rapids, probing and, on a machine without a pallet changer, loading. In our analysis, feed time is on average only 40 to 50 percent of overall run time.

Does putting more parts on the fixture always pay?

Run the numbers first. Load time grows as you add parts; the calculator estimates 8 seconds per extra part. In the worked example, load time rises from 24 to 104 seconds and parts per shift still rise about 26 percent, because each tool change now serves 12 parts.

Bottom Line

Workholding gets lost in the equation when working out the details of a manufacturing process. Much of the focus goes into the CNC machine, tooling and programming. Underestimating the impact of workholding on your productivity can be costly. There is gold to be mined in your manufacturing processes if you know where to look. So, how much are you leaving on the table each shift?

Sources and method. Feed-time share, the turntable inputs and every 1-part vs 16-part figure: PAWS Workholding, Hidden Opportunity in Workholding (downloadable analysis). The 2-part vs 12-part example: computed with the formulas of the PAWS Multiple Part Workholding ROI Calculator (revision R9), at 100 percent efficiency; inputs as listed above, annual quantity illustrative.


Related Posts


Optimizing Efficiency With a 4th Axis Workholding System

What to Look for in a Workholding Device

Custom Workholding Fixtures: Solutions That Make Sense

4 Questions to Ask Before Investing in CNC Workholding Equipment


Contact A Workholding Specialist

Questions? Contact us to speak with an engineer regarding your workholding application.

(866) 686-7297